Grousemount Wind Farm, the amalgamation of two previously permitted developments: Barnastooka (2010) and Grousemount (2012), received planning permission as a Strategic Infrastructure Development from An Bord Pleanala in June, 2016. For your information, please see all relevant Planning and Environmental documents submitted, and considered as a part of the An Bord Pleanala application.
Once completed the project, will comprise of four main elements:
The construction is expected to occur between 2017-2019, please see an indicative project timeline below for your information. As the project progresses, more detailed information relating to the project will be communicated via newsletter, public meetings and/or updates to the website.
Winter, 2017 | Spring/Summer, 2018 | Autumn/Winter, 2018 | Spring/Summer, 2019 |
---|---|---|---|
Initial construction site enabling works. |
Construction site access bridge at Roughty River. |
Ongoing development of wind turbine foundations, and access tracks. |
The continuation of wind turbine deliveries, and installation. |
Road widening at Sillahertane |
Initial development of wind turbine foundations, and access tracks. |
Construction of temporary bridge over Sullane River. |
The continuation of wind turbine deliveries, and installation. |
Ducting, and installation of underground cables at Coolea and Mullaghanish. |
Coomataggart 110 kV substation construction. |
Construction of temporary bridge over Sullane River. |
First generation, and commercial export of electricity. |
Ongoing cabling works. |
Community engagement. |
Community engagement. |
|
Community engagement. |